Technology

Data Center Infrastructure: Meta’s $25 Billion Debt Sale and the Jet Engines Powering the AI Boom

Data Center Infrastructure: Meta’s $25 Billion Debt Sale and the Jet Engines Powering the AI Boom

Two stories this week look unrelated. In one, Meta goes to the bond market for up to $25 billion. In the other, data center builders are buying retired airliner engines and bolting them to trailers to make electricity. They are the same story. AI infrastructure has become so expensive and so power-hungry that companies are borrowing at record scale to build it, and then scrambling for unconventional ways to turn it on. Here is what is happening, why it is happening now, and what it means.

Meta goes back to the bond market

Meta was seeking to raise between $20 billion and $25 billion in a bond sale, as the company ramps up spending on artificial intelligence infrastructure along with AI models and services. The deal was split across two currencies. It was expected to be two-thirds in U.S. dollars and one-third in euros.

The dollar portion has now priced. Meta sold $15 billion of dollar bonds across five tranches and drew peak demand of about $58 billion, roughly 3.9 times the size of the offering. The remainder is a euro offering, and it would be Meta’s first in euros. The dollar notes run from five to 30 years, while the euro portion runs from a little over four years to a little over 38. The final size of the euro leg was still to come at the time of writing, so check the latest terms if you are quoting figures.

This is not Meta’s first trip this year. It raised $25 billion in an April bond sale as well. Demand has cooled since then. The April deal drew peak orders of $96 billion, compared with about $58 billion this time.

Why borrow? Because the spending is enormous

The reason is capital expenditure. Meta now expects full-year capex of $135 billion to $145 billion, after raising the bottom of its earlier range by $5 billion in its third-quarter report. Much of that goes into data centers, chips and networking.

Debt is only one lever. Last week Meta said it plans to raise $95 billion for its AI initiatives, starting with $35 billion in underwritten public equity offerings and a further $60 billion through an at-the-market program. One report describes the broader capital-raising push as totaling nearly $120 billion, including a $60 billion at-the-market program and roughly $37.5 billion in common and preferred stock sales. Different outlets total these programs differently, so treat the exact sum as approximate.

Meta also uses structured financing for specific sites. For its Hyperion campus in Louisiana, reporting described a financing led by Blue Owl Capital, with Morgan Stanley structuring more than $27 billion in debt and about $2.5 billion in equity through a special purpose vehicle, an arrangement that lets Meta avoid carrying significant debt on its own balance sheet while acting as developer, operator and tenant. The same reporting says Hyperion can draw up to 5 gigawatts of power at full capacity. Keep that number in mind for the second half of this article.

The warning lights

Not everyone is relaxed about this. Days before the sale, S&P Global Ratings changed Meta’s outlook from AA- stable to AA- negative, citing uncertainty about its heavy capex and negative free cash flow. A fuller account says S&P affirmed the AA- rating but warned that AI capital spending could top $225 billion in 2027 and produce a $71 billion free operating cash flow deficit that year, with leverage possibly exceeding 1.0x.

Borrowing is also getting pricier. The longest bonds, due 2056, were set 2.2 percentage points above Treasuries, nearly 0.9 points wider than Meta’s similar April note. In plain terms, investors still want the bonds, but they are demanding more for the risk.

Not just Meta

This is a sector-wide pattern. Dealroom estimates that Alphabet, Meta, Oracle and Amazon have raised nearly $90 billion combined through bond sales since September. Earlier this year, Oracle’s $25 billion bond sale attracted a peak order book of $129 billion in February. Estimates of total hyperscaler spending are huge: one analysis says hyperscalers will spend more than $650 billion on AI infrastructure in 2026.

For readers who are not finance people, the takeaway is simple. The AI buildout is no longer funded purely out of profits. It is increasingly funded by debt and new share sales, which means the bet depends on AI revenue eventually catching up with the bills.

The bigger problem: money can’t buy electricity

Here is the catch. Raising $25 billion does not make a data center run. It needs power, and power is the scarce resource. Reports now describe electricity, not chips, as the main bottleneck. One analysis puts it this way: a new data center can be built in roughly one to three years, but the major grid work needed to power it can take five to fifteen.

Demand is rising fast. The IEA projects global data center electricity consumption roughly doubling from 485 TWh in 2025 to 950 TWh in 2030, and in the US data centers are expected to account for about half of all electricity demand growth through 2030.

Supply cannot keep pace, for several reasons:

  • Grid connection queues. In hubs like Northern Virginia, Phoenix and Dallas, connection waits that used to be one to two years now run four to seven. One report quotes utilities telling Google that interconnection can take “four or five, sometimes ten years”.
  • Equipment shortages. Large power transformer lead times average about 128 weeks and can reach five years. Another analysis says switchgear is sold out through 2028.
  • Delays everywhere. Roughly 30% to 50% of US data center capacity scheduled to open in 2026 is delayed or at risk of cancellation. Gartner’s projection is that 40% of AI data centers will be power-constrained by 2027.
  • Turbine scarcity. The Register reports that two-thirds of gas turbines for electricity generation come from three manufacturers: Japan’s MHI, Germany’s Siemens and GE Vernova, so a rush of orders creates a long queue.

A line of numbers from these sources varies a lot depending on the region and definition, so read them as a range rather than a single truth. The direction, however, is consistent: the wait for grid power is now longer than the time to build the building.

Enter the jet engines

If you cannot get the grid, you make your own power. And if you cannot get a new gas turbine, you look for something that is basically one already. That is where retired jet engines come in.

A gas turbine and a jet engine are close relatives. Data centers facing a gas turbine shortage are turning to aeroderivative turbines made from old jet engines. The idea is not new in industry. For decades, companies like GE Vernova and Siemens Energy have converted aviation engines for stationary power generation. What is new is the scale and the customer.

Some of the players:

  • ProEnergy. Each refurbished unit can generate up to 48 megawatts, enough for a small-to-medium data center or a town of 20,000 to 40,000 households. Companies supplying power for data centers, including some working with Google, say they will use ProEnergy turbines converted from jet engines, according to regulatory filings.
  • FTAI Aviation. It announced FTAI Power in December 2025 to convert retired CFM56 aircraft engines into 25-megawatt natural gas turbines for AI and cloud data centers, with commercial production expected to begin in 2026
  • xAI. Elon Musk’s xAI installed eight converted jet-engine turbines in Mississippi to help power its Colossus 2 data center in Memphis, according to the New York Times.
  • Boom Supersonic. In an interesting twist, the supersonic jet startup has begun selling a version of its jet’s engine as a power plant for data centers, and in September Crusoe walked away from a $1.25 billion deal to buy 29 of its natural gas turbines.

The appeal is speed. One person quoted by TechCrunch says that with jet-powered units, “they can have a data center running in 24 months”. The units are also modular, which suits a world where demand arrives in chunks. Industry commentary describes them as interim “bridge” power until permanent grid upgrades are completed, or as long-term peaking and backup capacity. And the plan is usually temporary: when grid power becomes available, the turbines are relegated to a backup role, used to supplement the grid, or sold on.

The scale of the untapped supply sounds almost comic. The Energy Information Administration said the engines from the 4,000 old military jets parked at a single desert base in Tucson could create 40,000 megawatts of power.

The catch: it is a stopgap, not a solution

Converted jet engines come with real trade-offs, and it would be misleading to present them as a clean fix.

  • Converted jet engines come with real trade-offs, and it would be misleading to present them as a clean fix.
  • Efficiency and pollution. TechCrunch, citing the Times, says converted jet engines are less efficient and pollute more than turbines designed for conventional gas plants, and it takes more of them to make the same power. The EIA also notes that factory-built turbines are likely to be better optimized for electricity generation than repurposed aircraft engines.
  • Not zero-carbon. One explainer sums it up: the turbines may deliver power faster than a grid connection, but they do not provide zero-carbon electricity. itechguides Noise and fuel use. Reports describe them as noisy and fuel-intensive, which matters when a site sits near homes
  • A new bottleneck. The same explainer warns that natural-gas infrastructure can become the new bottleneck.
  • Public pushback. A Gallup poll in May 2026 found that 71% of Americans oppose a local AI data center, 48% strongly. Diesel-like noise and emissions from on-site turbines do not help that case.

Policy is pushing in the same direction, though. TechCrunch notes that the Trump administration is adding to the pressure by encouraging data centers to generate their own electricity.

Other “extreme measures” on the table

Jet engines are the memorable example, but they are one of several workarounds. Operators and analysts mention:

  • Microgrids and batteries. The data center microgrid and battery storage markets are each forecast to grow at 14.2% a year from 2026 to 2036.
  • Fuel cells. One of the alternatives to gas turbines for on-site power, along with diesel generators and co-locating facilities with wind farms.
  • Nuclear, including small modular reactors, which are being discussed as a longer-term answer but will not solve a problem that bites in the next two or three years.
  • Better efficiency. Some guides now argue that “tokens-per-watt” is the efficiency metric that matters most in 2026, reflecting the idea that getting more AI out of every unit of power is as valuable as finding more power.

What this means

For investors and the industry, the story is a leveraged bet. Meta, Oracle, Alphabet and Amazon are borrowing at unprecedented scale because they believe AI revenue will justify it. Rating agencies are not saying they are wrong, but they are watching. S&P’s negative outlook and the wider spreads are the market’s way of asking for proof.

For energy and communities, the story is uncomfortable. The fastest way to get power today is often on-site gas, which is more polluting, and local opposition is already high. Data centers also push up demand on shared grids. One analysis notes that retail electricity prices have risen 42% since 2019, although many factors drive that.

For everyone else, it is a reminder that “the cloud” is physical. Behind every chatbot reply is a building, a substation, a transformer with a multi-year waiting list, and increasingly a turbine that used to fly passengers.

Frequently Asked Questions

Why is Meta borrowing so much money?

Because its AI spending is enormous. Meta expects full-year capex of $135 billion to $145 billion, and it is funding part of that through bonds, share sales and project-level financing rather than relying only on operating cash flow.

Are old jet engines really powering data centers?

Yes, in the sense that retired aircraft engine cores are rebuilt into stationary gas turbines called aeroderivatives. Companies like ProEnergy and FTAI are doing this, and xAI has installed converted turbines in Mississippi. They are not plugged in as-is, and the output units range from roughly 25 to 48 megawatts each.

Why not just connect to the grid?

In many major markets the wait for a new large connection now runs years, and the transformers and switchgear needed are on long backorder. A data center can be built much faster than the grid can serve it, so some operators generate their own power in the meantime.

Are jet-engine turbines good for the environment?

No, they are a trade-off. They burn natural gas, are less efficient than purpose-built turbines, and emit more per unit of power. They are mainly a bridge until grid power or cleaner supply is available.

Key takeaways

  • Meta is raising up to $25 billion in bonds, with a $15 billion dollar tranche priced at about 3.9 times oversubscription and a first-ever euro leg to follow
  • The money funds an AI buildout so large that Meta guides to $135 billion to $145 billion in capex this year, and S&P has moved its outlook to negative
  • Big Tech borrowing is a sector-wide pattern, with nearly $90 billion raised by four hyperscalers since September
  • The deeper constraint is power: data centers go up in one to three years, but grid connection can take years longer
  • Retired jet engines, converted into 25 to 48 megawatt turbines, are a fast but less efficient and higher-polluting stopgap
  • The real test is whether AI revenue grows fast enough to justify both the debt and the infrastructure